Further design was commissioned by Ewing VDM for the on-island facilities including, drainage designs, and upgrades to existing roads and hardstand areas.
A requirement was for all culverts to be designed to ensure the existing tidal movements were not negatively impacted.
Design of road embankment earthworks was challenging due to being located on mudflats across to Finucane Island. JDSi oversaw the embankment and pavement design process and developed a design solution requiring extensive use of geotextiles to support earthworks and control settlement underneath the road embankment areas.
With the Finucane Island access road being a public road, designs had to accommodate the shared road usage with large road trains and light vehicles. MRWA and the Town of Port Hedland specified tight safety controls and design guidelines during the documentation and design process.